     Projects:

Midpoint to Hailey
Gateway
Boardman
B2H
Arrow Rock
Placerville
Portico
TVMP
Weatherby
Project: Midpoint to Hailey



This project was an upgrade and redesign of an existing transmission line north of Picabo, Idaho and consisted of retro-fitting metal structures to three existing wooden H-frame structures, and constructing a new three-pole structure at a line angle point . Timberline Surveying provided the control network and topographic asbuilt survey of the existing conductors and structures for design. Timberline Surveying provided construction staking for the modifications to the existing and replacement structures and re-sagging of all of the modified lines. The retro-fit surveying included coordination with the Idaho Power crews to align the new metal structures as they were flown in by helicopter, at three separate locations simultaneously. On this project, Timberline provided eight crews to facilitate the timeline.